1/25/2013 - Sewer Work - Weekly Look Ahead 1/28/13 through 2/01/13

Sewer Work 1/28/13 through 2/01/13


All main line sewer is now installed for contract IV,
North Nichols area.

Crew #1;

Sanitary sewer connections - Dogwood Lane.
Sanitary sewer testing - Dogwood La. to Teeter Rock Rd.