[ARCHIVED] Town of Trumbull Paving Updates

Road Work Sign (JPG)

Beginning Tuesday, August 10, 2021, work will begin in three areas of town. All work is weather dependent.

SHELTON ROAD

Milling will begin on Shelton Road on August 10th. Equipment will be staged on Cemetery Rd prior to the start date. Milling should be completed in 5-6 hours. Police will direct traffic on Shelton Rd.

Paving of Shelton Rd is scheduled to begin Thursday, August 12th, weather permitting. Additional work will be required in the future.

DANIELS FARM ROAD

After milling is completed on Shelton Rd, crews will move to emergency repair work on Daniels Farm Rd. Milling will continue through the afternoon of Wednesday, August 11th.

Once Shelton Rd is paved, the Daniels Farm repair work will be paved. Again, police will direct traffic on Daniels Farm Rd. 

GREAT NECK ROAD AREA

After the milling of Shelton Rd and the Daniels Farm Rd emergency repairs is completed, milling equipment will move to the Great Neck Rd area. Great Neck Rd, Willow Lane, Laurie Rd, Woodmere Dr, and Fawn Circle will be milled. The milling should be completed by Monday, August 16th.

The Great Neck Rd area will be leveled so that town crews can complete structural adjustments before final paving. This round of paving should take 5 days. Updates to this project will be made as the schedule is refined. Again, this work is weather dependent.

ALL ROADS WILL BE OPEN TO EMERGENCY VEHICLES DURING MILLING AND PAVING WORK.  SOME DETOURS MAY BE REQUIRED.