The Route 111 Signal Installation, Roadway and Trail Improvement Project near the Fitness Edge Plaza on Monroe Turnpike is nearing completion over the next few weeks. To keep the community advised as to the anticipated construction and potential traffic in the area, the following schedule of milling, paving and traffic signal activation is provided below. Please know the schedule is considered a guide and can change due to weather or unforeseen conditions.
For the milling and paving, police officers will be present to direct traffic into and out of the plaza driveway. The work hours are expected to be between 7 AM and 3:30 PM.
Route 111 Construction Schedule
- Monday – Thursday, July 20, 2023 – Milling & Paving
- Friday, July 21, 2023 – Traffic Signal Placed in Flashing Operation (yellow flashing for Route 111; red flashing for plaza driveway) by this date
- Friday, July 21, 2023 – Monday, July 24th – Apply Pavement Markings & Signage
- Wednesday July 26, 2023 – Traffic Signal Activation
Please contact William Maurer, Town Engineer at 203-452-5050 or wmaurer@trumbull-ct.gov with any questions.
Expect delays through the area, both on Route 111 and Route 25. We apologize for the inconvenience and appreciate your patience.