Moose Hill Road Construction

Project Description

The Town of Trumbull Engineering Department is currently working on a Roadway Reconstruction of Moose Hill Road.

Work will continue until the end of 2019 (weather permitting). Various sections of the road will be closed to through traffic at different times throughout this process. The Town of Trumbull will endeavor to keep disturbance to a minimum.  However, your patience will be much appreciated.  Construction work is anticipated to start at 7:00 AM daily.  All bus stops will remain at their current locations.

Road Work Sign (JPG)

Project Progress

The Town will post updates to this website and include the anticipated two week look ahead for the project. Dates and locations are subject to change if unforeseen factors arise. Dayton Construction is the contractor working for the Town on the Moose Hill Road Reconstruction project.

12/06/19: 2 Week Look Ahead

Week of December 9th , 2019:

  • Paving and repair of driveway aprons

Week of December 16th , 2019:

  • Paving and repair of driveway aprons
  • Pavement markings to be applied


11/27/19: 2 Week Look Ahead

Week of December 2nd , 2019

  • Paving top course to continue
  • Paving and repair of driveway aprons
  • Pavement markings to be applied

Week of December 9th, 2019

  • Paving and repair of driveway aprons
  • Pavement markings to be applied

11/22/19: 2 Week Look Ahead

Week of November 25th, 2019

  • Paving top course to continue

Week of December 2nd, 2019

  • Paving top course to continue

11/15/19: 2 Week Look Ahead

Week of November 18th, 2019

  • Paving top course beginning from the North side

Week of November 25th, 2019

  • Paving top course to continue

11/08/19: 2 Week Look Ahead

Week of November 11th, 2019

  • Landscaping and Plantings to continue

Week of November 18th, 2019

  • Paving top course to begin

11/01/19: 2 Week Look Ahead

Week of November 4th, 2019

  • Landscaping and Plantings to continue
  • Paving of top course to begin

Week of November 11th, 2019

  • Paving top course to continue

10/25/19: 2 Week Look Ahead

Week of October 28th, 2019

  • Landscaping and Plantings to continue
  • Paving to continue

Week of November 4th, 2019

  • Landscaping and Plantings to continue
  • Paving to continue

9/27/19: 2 Week Look Ahead

Week of September 30th, 2019

  1. Underdrain installation to continue
  2. Catch basins to be brought to final grade

Week of October 7th, 2019

  1. Fine grading of road
  2. Paving to continue