Strobel Road Construction

Project Description

The Town of Trumbull Engineering Department is currently working on a Roadway Reconstruction of Strobel Road (from Daniels Farm Road to Booth Hill Road). 

The scope of work will include intersection improvements at Daniels Farm Road, culvert improvements, roadway re-alignment, full depth roadway reconstruction and drainage improvements, etc.

This is a long-term project that will require multiple years to complete (weather dependent). Location of work along Strobel Road will be updated as the project progresses. Various sections of the road will be closed to through traffic at different times throughout this process.  The Town of Trumbull will endeavor to keep disturbance to a minimum.  However, your patience will be much appreciated. Construction work is anticipated to start at 7:00 AM daily.  All bus stops will remain at their current locations.

The State of Connecticut will provide 100% of the construction costs and the Town of Trumbull was only required to fund the design of the project.

Road Work Sign (JPG)

Project Progress

The Town will post updates to this website and include the anticipated two week look ahead for the project. Dates and locations are subject to change if unforeseen factors arise. Colonna Concrete & Asphalt Paving LLC is the contractor working for the Town on the Strobel Road Reconstruction project.

12/06/19: 2 Week Look Ahead

Starting on November 18, 2019, the contractor will begin work between Chatham Drive and Daniels Farm Road. This work will be limited to drainage improvements within or close to the roadway shoulder. 2-lane traffic will be maintained at all times. Current Phase 2 detour from Chatham Drive to Gray Rock Road will remain active until further notice.

Detour Map: ACTIVE Strobel Road Detour Plans-Chatham Dr to Gray Rock Rd Work Zones (PDF)

Week of December 9th , 2019:

  • Continue to furnish and install drainage
  • Continue clearing and grubbing
  • Construction layout and establish grade for road reconstruction
  • Installation of sediment and erosion control devices to continue 

Week of December 16th , 2019:

  • Continue to furnish and install drainage
  • Continue clearing and grubbing
  • Construction layout and establish grade for road reconstruction
  • Installation of sediment and erosion control devices to continue

11/27/19: 2 Week Look Ahead

Starting on November 18, 2019, the contractor will begin work between Chatham Drive and Daniels Farm Road. This work will be limited to drainage improvements within or close to the roadway shoulder. 2-lane traffic will be maintained at all times. Current Phase 2 detour from Chatham Drive to Gray Rock Road will remain active until further notice.

Detour Map: ACTIVE Strobel Road Detour Plans-Chatham Dr to Gray Rock Rd Work Zones (PDF)

Week of December 2nd , 2019 

  • Continue to furnish and install drainage
  • Continue clearing and grubbing
  • Construction layout and establish grade for road reconstruction
  • Installation of sediment and erosion control devices to continue

Week of December 9th , 2019 

  • Continue to furnish and install drainage
  • Continue clearing and grubbing
  • Construction layout and establish grade for road reconstruction
  • Installation of sediment and erosion control devices to continue


11/22/19: 2 Week Look Ahead

Starting on November 18, 2019, the contractor will begin work between Chatham Drive and Daniels Farm Road. This work will be limited to drainage improvements within or close to the roadway shoulder. 2-lane traffic will be maintained at all times. Current Phase 2 detour from Chatham Drive to Gray Rock Road will remain active until further notice.

Week of November 25th , 2019 

  • Continue to furnish and install drainage
  • Continue clearing and grubbing
  • Construction layout and establish grade for road reconstruction
  • Installation of sediment and erosion control devices to continue

Week of December 2nd , 2019 

  • Continue to furnish and install drainage
  • Continue clearing and grubbing
  • Construction layout and establish grade for road reconstruction
  • Installation of sediment and erosion control devices to continue

11/15/19: 2 Week Look Ahead

Starting on November 18, 2019, the contractor will begin work between Chatham Drive and Daniels Farm Road. This work will be limited to drainage improvements within or close to the roadway shoulder. 2-lane traffic will be maintained at all times. Current Phase 2 detour from Chatham Drive to Gray Rock Road will remain active until further notice.

Week of November 18th , 2019 

  • Continue to furnish and install drainage
  • Continue clearing and grubbing
  • Construction layout and establish grade for road reconstruction
  • Installation of sediment and erosion control devices to continue

Week of November 25th , 2019 

  • Continue to furnish and install drainage
  • Continue clearing and grubbing
  • Construction layout and establish grade for road reconstruction
  • Installation of sediment and erosion control devices to continue

10/18/2019: 2 Week Look Ahead

Week of October 21st , 2019

  • Continue to furnish and install drainage
  • Continue clearing and grubbing
  • Construction layout and establish grade for road reconstruction
  • Installation of sediment and erosion control devices to continue

Week of October 28th , 2019

  • Continue to furnish and install drainage
  • Continue clearing and grubbing
  • Construction layout and establish grade for road reconstruction
  • Installation of sediment and erosion control devices to continue

10/04/2019: 2 Week Look Ahead

Week of October 7th , 2019 

  • Construction and detour are scheduled to resume on Monday, October 7th
  • Tree removal to continue
  • Construction layout to establish grade line
  • Installation of sediment and erosion control devices

Week of October 14th , 2019 

  • Tree removal to continue
  • Construction layout to establish grade line
  • Installation of sediment and erosion control devices

10/2/19: STROBEL ROAD UPDATE

Strobel Road construction is expected to resume the week of October 7, 2019.

--------------------------------------------------------

Detour for Strobel Road Reconstruction

The contractor will close lower Strobel Road from Gray Rock Road to Booth Hill Road, Monday through Friday, from 8:30 AM to 4:30 PM until further notice.

The roadway will be open to traffic Monday through Friday after 4:30PM and on the weekends.  During the time of construction, emergency vehicles and school buses will be allowed through at all times.

School buses will pick up and drop off students at their respective bus stops.

A detour for this area for all vehicular traffic, other than emergency vehicles and school buses, will be in effect from 8:30 AM to 4:30 PM, Monday through Friday. The detour is as follows:

Booth Hill Road to Pilgrim Lane to Beacon Hill Road to Stoneleigh Road to Gray Rock Road to Strobel Road and the reverse.

For residents travelling North on Pinewood Trail, the detour will start at Bear Den Road to Hemlock Trail.

Detour for Strobel Road Reconstruction

Detour signs will be posted to assist drivers in this area.

Please visit the Town and the Board of Education websites for additional information and updates about this project.

Thank you.

9/27/2019: 2 Week Look Ahead

Week of September 30th , 2019

An unforeseen issue has arisen and is currently being addressed. Construction is expected to resume shortly. An updated schedule will be provided this week.

9/27/19: Strobel Road Update

Strobel Road construction is expected to resume the week of October 7, 2019.

--------------------------------------------------------

Detour for Strobel Road Reconstruction

Important information from First Selectman Tesoro about the Strobel Road construction project:

This project was scheduled to begin this Thursday, August 29, 2019. As that is the first day of school, I have delayed the start of the project to next Tuesday, September 3rd at 7AM. You may see some minor construction activity over the next 2 days, but there will be no road closures or detours until next Tuesday.

Beginning on September 3rd, the contractor will close lower Strobel Road from Gray Rock Road to Booth Hill Road, Monday through Friday, from 8:30 AM to 4:30 PM until further notice.

The roadway will be open to traffic Monday through Friday after 4:30PM and on the weekends.

During the time of construction, emergency vehicles and school buses will be allowed through at all times.

School buses will pick up and drop off students at their respective bus stops.

A detour for this area for all vehicular traffic, other than emergency vehicles and school buses, will be in effect from 8:30 AM to 4:30 PM, Monday through Friday. The detour is as follows:

Booth Hill Road to Pilgrim Lane to Beacon Hill Road to Stoneleigh Road to Gray Rock Road to Strobel Road and the reverse.

For residents travelling North on Pinewood Trail, the detour will start at Bear Den Road to Hemlock Trail.

Detour for Strobel Road Reconstruction

Detour signs will be posted to assist drivers in this area.

Please visit the Town and the Board of Education websites for additional information and updates about this project.

Thank you.

9/19/19: Strobel Road Update

A minor, unforeseen issue has arisen and is being addressed. Construction will resume shortly.  An update will be provided on the town website when construction resumes. Thank you for your continued patience.

--------------------------------------------------------

Detour for Strobel Road Reconstruction

Important information from First Selectman Tesoro about the Strobel Road construction project:

This project was scheduled to begin this Thursday, August 29, 2019. As that is the first day of school, I have delayed the start of the project to next Tuesday, September 3rd at 7AM. You may see some minor construction activity over the next 2 days, but there will be no road closures or detours until next Tuesday.

Beginning on September 3rd, the contractor will close lower Strobel Road from Gray Rock Road to Booth Hill Road, Monday through Friday, from 8:30 AM to 4:30 PM until further notice.

The roadway will be open to traffic Monday through Friday after 4:30PM and on the weekends.

During the time of construction, emergency vehicles and school buses will be allowed through at all times.

School buses will pick up and drop off students at their respective bus stops.

A detour for this area for all vehicular traffic, other than emergency vehicles and school buses, will be in effect from 8:30 AM to 4:30 PM, Monday through Friday. The detour is as follows:

Booth Hill Road to Pilgrim Lane to Beacon Hill Road to Stoneleigh Road to Gray Rock Road to Strobel Road and the reverse.

For residents travelling North on Pinewood Trail, the detour will start at Bear Den Road to Hemlock Trail.

Detour for Strobel Road Reconstruction

Detour signs will be posted to assist drivers in this area.

Please visit the Town and the Board of Education websites for additional information and updates about this project.

Thank you.