Road Paving Program

Project Description

The Town of Trumbull Road Paving Program is dedicated to repairing various roads surface and subsurface infrastructure. This includes repairs to the drainage and sanitary systems that have been previously inspected.

Various sections of the road will be closed to through traffic at different times throughout this process. The Town of Trumbull will endeavor to keep disturbance to a minimum. However, your patience will be much appreciated. Construction work is anticipated to start at 7:00 AM daily.  All bus stops will remain at their current locations.

Road Work Sign (JPG)

Project Progress

The Town will post updates to this website and include the anticipated two week look ahead for the project. Dates and locations are subject to change if unforeseen factors arise.

12/06/2019: 2 Week Look Ahead

Week of December 9th , 2019:

  1. Drainage repairs to continue on Campbell Road and Richfield Road

  2. Drainage Repairs to begin on Madison Ave between Tashua Road and Newton Lane

Week of December 16th , 2019:

  1. Drainage repairs to continue on Madison Ave between Tashua Road and Newton Lane

11/27/19: 2 Week Look Ahead

Week of December 2nd , 2019:

  • Drainage repairs to continue on Campbell Road and Richfield Road

Week of December 9th , 2019:

  • Drainage repairs to continue on Campbell Road and Richfield Road

11/22/19: 2 Week Look Ahead

Week of November 25th , 2019:

  • Drainage repairs to continue on Campbell Road and Richfield Road

Week of December 2nd , 2019:

  • Drainage repairs to continue on Campbell Road and Richfield Road

11/15/19: 2 Week Look Ahead

Week of November 18th , 2019:

  • Drainage repairs to continue on Elmwood and Walnut Avenue 

Week of November 25th , 2019:

  • Drainage repairs to continue on Elmwood and Walnut Avenue
  • Drainage repairs to begin on Campbell Road and Richfield Road

11/08/19: 2 Week Look Ahead

Week of November 11th , 2019:

  • Drainage repairs to continue on Elmwood and Walnut Avenue

Week of November 18th , 2019:

  • Drainage repairs to continue on Elmwood and Walnut Avenue
  • Drainage repairs to begin on Campbell Road and Richfield Road

11/01/19: 2 Week Look Ahead

Week of November 4th , 2019:

  • Drainage repairs to continue on Elmwood and Walnut Avenue 

Week of November 11th , 2019:

  • Drainage repairs to continue on Elmwood and Walnut Avenue

10/25/19: 2 Week Look Ahead

Week of October 28th , 2019:

  • Drainage repairs to continue on Abric Drive, Green Street, and Bonheur Road
  • Drainage repairs to begin on Elmwood and Walnut Avenue 

Week of November 4th , 2019:

  • Drainage repairs to continue on Elmwood and Walnut Avenue

10/18/2019: 2 Week Look Ahead

Week of October 21st , 2019:

  1. Drainage repairs to continue on Abric Drive, Green Street, and Bonheur Road
  2. Drainage repairs to begin on Elmwood and Walnut Avenue

Week of October 28th , 2019:

  1. Drainage repairs to continue on Abric Drive, Green Street, and Bonheur Road
  2. Drainage repairs to continue on Elmwood and Walnut Avenue

9/27/19: 2 Week Look Ahead

Week of September 30rd, 2019:

1.    Drainage repairs to continue on Old Dike Road

2.    Landscaping and repairs to driveway aprons to begin on Woodridge Circle and Judson Street

3.    Landscaping and repairs to driveway aprons to begin on Rocky Hill Rd and Rocky Hill Terrace

4.    Drainage repairs to begin on Abric Drive, Green Street, and Bonheur Road

Week of October 7th, 2019:

1.    Landscaping and repairs to driveway aprons to begin on Woodridge Circle and Judson Street

2.    Landscaping and repairs to driveway aprons to begin on Rocky Hill Rd and Rocky Hill Terrace

3.    Drainage repairs to begin on Abric Drive, Green Street, and Bonheur Road