Road Paving Program

Project Description

The Town of Trumbull Road Paving Program is dedicated to repairing various roads surface and subsurface infrastructure. This includes repairs to the drainage and sanitary systems that have been previously inspected.

Various sections of the road will be closed to through traffic at different times throughout this process. The Town of Trumbull will endeavor to keep disturbance to a minimum. However, your patience will be much appreciated. Construction work is anticipated to start at 7:00 AM daily.  All bus stops will remain at their current locations.

Pavement Condition Index Map

The current Pavement Condition Map being updated.

Road Work Sign (JPG)

Project Progress

The Town will post updates to this website and include the anticipated two week look ahead for the project. Dates and locations are subject to change if unforeseen factors arise.

10/30/25: 2 Week Look Ahead

Week of 11/03/25:

  • Drainage Repairs to continue on Oak Ridge Road, Hillston Road, Qual Trail, and Bob White Lane
  • Connecticut Department of Transportation will be milling and resurfacing the Trumbull Commuter Lot at Penny Avenue. Work is scheduled to occur on Sunday, November 2 and be completed on Wednesday November 5, 2025

Week of 11/10/25:

  • Drainage Repairs to continue on Oak Ridge Road, Hillston Road, Qual Trail, and Bob White Lane

10/17/25: 2 Week Look Ahead

Week of 10/20/25:

  • Drainage Repairs to begin on Oak Ridge Road, Hillston Road, Qual Trail, and Bob White Lane
  • FOG Sealing Roads to continue on the following roads:

    Ridgeview Avenue

    Meadowview Drive East

    Meadowview Drive West

    Oakland Drive

    Clemens Avenue

    Ann Street

    Meadow Road

    Cook Circle

    Wedgewood Road

    Meadow Road

Week of 10/27/25:

  • Drainage Repairs to continue on Oak Ridge Road, Hillston Road, Qual Trail, and Bob White Lane

9/18/25: 2 Week Look Ahead

Week of 9/22/25:

  • Drainage Repairs to continue on Westfield Drive, Bull Frog Lane, Crabapple Road, Fuller Road, Horse Tavern Road, Post Gate Road and Blue Jay Drive

Week of 9/29/25:

  • FOG Sealing Roads to start on or about week of 9/29/2025 on the following roads:

    Ridgeview Avenue

    Meadowview Drive East

    Meadowview Drive West

    Oakland Drive

    Clemens Avenue

    Ann Street

    Meadow Road

    Cook Circle

    Wedgewood Road

    Meadow Road


  • Drainage Repairs to continue on Westfield Drive, Bull Frog Lane, Crabapple Road, Fuller Road, Horse Tavern Road, Post Gate Road and Blue Jay Drive


8/29/25: 2 Week Look Ahead

Week of 9/1/25:

  • Drainage Repairs to continue on Westfield Drive, Bull Frog Lane, Crabapple Road, Fuller Road, Horse Tavern Road, Post Gate Road and Blue Jay Drive

Week of 9/8/25:

  • Drainage Repairs to continue on Westfield Drive, Bull Frog Lane, Crabapple Road, Fuller Road, Horse Tavern Road, Post Gate Road and Blue Jay Drive

7/25/25: 2 Week Look Ahead

Week of 7/28/25:

  • Milling and Paving of roadway to continue on Asbury Road, Stemway Road, Raven Road, Wedgewood Road, Old Coach Lane, Fieldcrest Drive, West Rock Road, Thornwood Place, Sanford Ave, Meadowview Drive, Echo Hill Road, Thomas Street and North Lynwood Drive
  • Drainage Repairs to continue on Salem Road, Sabina Road, Jamestown Road and Crocus Lane
  • Lake Avenue will be closed on Monday, July 28th, between Garwood Road and Wildwood Drive. Bore testing is expected to begin at 7:30am and will end by 4:00pm. A detour will be in place directing traffic via Garwood and Wildwood

Week of 8/4/25:

  • Driveway and curb repair to continue on Asbury Road, Stemway Road, Raven Road, Wedgewood Road, Old Coach Lane, Fieldcrest Drive, West Rock Road, Thornwood Place, Sanford Ave, Meadowview Drive, Echo Hill Road, Thomas Street and North Lynwood Drive
  • Drainage Repairs to continue on Salem Road, Sabina Road, Jamestown Road and Crocus Lane


7/10/25: 2 Week Look Ahead

Week of 7/14/25:

  • Landscape repairs to continue on Country Lane, Elaine Place, Four Seasons Lane, Ivywood Place, Koger Road, Leonard Place, Merwin Street, Raynor Ave and Raynor Place
  • Drainage Repairs to continue on Salem Road, Sabina Road, Jamestown Road and Crocus Lane
  • Milling and Paving of roadway to continue on Asbury Road, Stemway Road, Raven Road, Wedgewood Road, Old Coach Lane, Fieldcrest Drive, West Rock Road, Thornwood Place, Sanford Ave, Meadowview Drive, Echo Hill Road, Thomas Street and North Lynwood Drive

Week of 7/21/25:

  • Milling and Paving of roadway to continue on Asbury Road, Stemway Road, Raven Road, Wedgewood Road, Old Coach Lane, Fieldcrest Drive, West Rock Road, Thornwood Place, Sanford Ave, Meadowview Drive, Echo Hill Road, Thomas Street and North Lynwood Drive


7/03/25: 2 Week Look Ahead

Week of 7/07/25:

  • Landscape repairs to continue on Country Lane, Elaine Place, Four Seasons Lane, Ivywood Place, Koger Road, Leonard Place, Merwin Street, Raynor Ave and Raynor Place
  • Drainage Repairs to continue on Salem Road, Sabina Road, Jamestown Road and Crocus Lane
  • Milling and Paving of roadway to continue on Asbury Road, Stemway Road, Raven Road, Wedgewood Road, Old Coach Lane, Fieldcrest Drive, West Rock Road, Thornwood Place, Sanford Ave, Meadowview Drive, Echo Hill Road, Thomas Street and North Lynwood Drive
  • Drainage repairs to continue on Beers and Elizabeth Street

Week of 7/14/25:

  • Landscape repairs to continue on Country Lane, Elaine Place, Four Seasons Lane, Ivywood Place, Koger Road, Leonard Place, Merwin Street, Raynor Ave and Raynor Place
  • Drainage Repairs to continue on Salem Road, Sabina Road, Jamestown Road and Crocus Lane
  • Milling and Paving of roadway to continue on Asbury Road, Stemway Road, Raven Road, Wedgewood Road, Old Coach Lane, Fieldcrest Drive, West Rock Road, Thornwood Place, Sanford Ave, Meadowview Drive, Echo Hill Road, Thomas Street and North Lynwood Drive

6/06/25: 2 Week Look Ahead

Week of 6/09/25:

  • Drainage Repairs to continue on Echo Hill Road, Hazelnut Drive, Lynwood Drive, Meadowview Drive and Thomas Street
  • Landscape repairs to continue on Juniper Circle, Juniper Ridge Rd, Knollcrest Dr, Pauline St, Pepperidge Rd, Round Hill Rd, Stella St, and Vazzano 
  • Leveling and Paving of roadway to continue on Country Lane, Elaine Place, Four Seasons Lane, Ivywood Place, Koger Road, Leonard Place, Merwin Street, Raynor Ave and Raynor Place
  • Unity Park Paving to continue 
    • Intermittent closures are expected during the day while construction takes place

Week of 6/16/25:

  • Drainage Repairs to continue on Echo Hill Road, Hazelnut Drive, Lynwood Drive, Meadowview Drive and Thomas Street
  • Landscape repairs to continue on Juniper Circle, Juniper Ridge Rd, Knollcrest Dr, Pauline St, Pepperidge Rd, Round Hill Rd, Stella St, and Vazzano
  • Paving of roadway to continue on Country Lane, Elaine Place, Four Seasons Lane, Ivywood Place, Koger Road, Leonard Place, Merwin Street, Raynor Ave and Raynor Place
  • Drainage Repairs to begin on Salem Road, Sabina Road, Jamestown Road and Crocus Lane
  • Milling of roadway to begin on Asbury Road, Stemway Road, Raven Road, Wedgewood Road, Old Coach Lane, Fieldcrest Drive, West Rock Road, Thornwood Place, Sanford Ave, Meadowview Drive, Echo Hill Road, Thomas Street and North Lynwood Drive
  • Unity Park Paving to continue 
    • Intermittent closures are expected during the day while construction takes place


6/02/25: 2 Week Look Ahead

Week of 6/02/25:

  • Drainage Repairs to continue on Echo Hill Road, Hazelnut Drive, Lynwood Drive, Meadowview Drive and Thomas Street
  • Driveway apron and Landscape repair to continue on Juniper Circle, Juniper Ridge Rd, Knollcrest Dr, Pauline St, Pepperidge Rd, Round Hill Rd, Stella St, and Vazzano 
  • Leveling and Paving of roadway to continue on Country Lane, Elaine Place, Four Seasons Lane, Ivywood Place, Koger Road, Leonard Place, Merwin Street, Raynor Ave and Raynor Place
  • Unity Park Paving to continue 
    • Intermittent closures are expected during the day while construction takes place

Week of 6/9/25:

  • Drainage Repairs to continue on Echo Hill Road, Hazelnut Drive, Lynwood Drive, Meadowview Drive and Thomas Street
  • Landscape repairs to continue on Juniper Circle, Juniper Ridge Rd, Knollcrest Dr, Pauline St, Pepperidge Rd, Round Hill Rd, Stella St, and Vazzano 
  • Leveling and Paving of roadway to continue on Country Lane, Elaine Place, Four Seasons Lane, Ivywood Place, Koger Road, Leonard Place, Merwin Street, Raynor Ave and Raynor Place


5/09/25: 2 Week Look Ahead

Week of 5/12/25:

  • Drainage Repairs to continue on Raven Road and Fieldcrest Road
  • Paving of Juniper Circle, Juniper Ridge Rd, Knollcrest Dr, Pauline St, Pepperidge Rd, Round Hill Rd, Stella St, and Vazzano to continue
  • Unity Park Paving to continue 
    • Intermittent closures are expected during the day while construction takes place

Week of 5/19/25:

  • Drainage Repairs to begin on Echo Hill Road, Hazelnut Drive, Lynwood Drive, Meadowview Drive and Thomas Street
  • Milling and Paving to begin on Old Town Road from Cumberland Drive to Red Oak Road
  • Driveway and Curb repair to begin on Juniper Circle, Juniper Ridge Rd, Knollcrest Dr, Pauline St, Pepperidge Rd, Round Hill Rd, Stella St, and Vazzano to continue
  • Milling and Paving to begin on Country Lane, Elaine Place, Four Seasons Lane, Ivywood Place, Koger Road, Leonard Place, Merwin Street, Raynor Ave and Raynor Place


4/16/25: 2 Week Look Ahead

Week of 4/21/25:

  • Drainage Repairs to continue on Wedgewood Road, Old Coach Ln, West Rock Road and Thornwood Place
  • Drainage Repairs to begin on Raven Road and Fieldcrest Road
  • Milling and Paving of Juniper Circle, Juniper Ridge Rd, Knollcrest Dr, Pauline St, Pepperidge Rd, Round Hill Rd, Stella St, and Vazzano to continue
  • Unity Park 
    •  Improvements behind Unity #1 press box and concession stand are scheduled to begin Monday April 21st.  Pedestrian access to this area will be limited
    • Pavement reclamation and re-paving of Unity Park Road are scheduled to begin April 21st. Intermittent closures are expected during the day while construction takes place

Week of 4/28/25:

  • Drainage Repairs to continue on Raven Road and Fieldcrest Road
  • Milling and Paving of Juniper Circle, Juniper Ridge Rd, Knollcrest Dr, Pauline St, Pepperidge Rd, Round Hill Rd, Stella St, and Vazzano to continue

4/3/25: 2 Week Look Ahead

Week of 4/07/25:

  • Drainage Repairs to continue on Wedgewood Road, Old Coach Ln, West Rock Road and Thornwood Place
  • Driveway aprons to be cut in preparation for paving of Juniper Circle, Juniper Ridge Rd, Knollcrest Dr, Pauline St, Pepperidge Rd, Round Hill Rd, Stella St, and Vazzano Pl 

Week of 4/14/25:

  • Drainage Repairs to continue on Wedgewood Road, Old Coach Ln, West Rock Road and Thornwood Place
  • Begin Milling and Paving of Juniper Circle, Juniper Ridge Rd, Knollcrest Dr, Pauline St, Pepperidge Rd, Round Hill Rd, Stella St, and Vazzano 

9/13/24: 2 Week Look Ahead

Week of 9/16/24:

  • Drainage repairs to begin on Round Hill Road
  • Drainage Repairs to Begin on Lake Avenue
  • Sanitary Sewer repairs to continue on Old Town Road

Week of 9/23/24:

  • Drainage repairs to continue on Round Hill Road
  • Drainage Repairs to continue on Lake Avenue
  • Sanitary Sewer repairs to continue on Old Town Road

8/20/24: 2 Week Look Ahead

Week of 8/19/24:

  • Fog sealing will begin Wednesday, August 21st on Nuthatch Hill Rd area, Chalon, Bayberry Road area, Barn Swallow Drive, and Wildfire Lane.  All work is weather-dependent
  • Paving on Val-de-mere Ave, Twin Brooks Park, Rocky Ridge Dr, Beech Tree Cir, Blueberry Rd, Berry Ln. 
  • Paving to begin at Twin Brooks Park
  • Drainage repairs to continue on Country Ln, Deerfield Dr, Elaine Pl, Four Seasons Ln, Ivywood Pl and Leonard Pl
  • Sanitary Sewer repairs to begin on Old Town Road

Week of 8/26/24:

  • Paving to continue on Val-de-mere Ave, Twin Brooks Park, Rocky Ridge Dr, Beech Tree Cir, Blueberry Rd, Berry Ln. 
  • Paving to continue at Twin Brooks Park
  • Drainage repairs to continue on Country Ln, Deerfield Dr, Elaine Pl, Four Seasons Ln, Ivywood Pl and Leonard Pl
  • Sanitary Sewer repairs to continue on Old Town Road


8/2/24: 2 Week Look Ahead

Week of 8/5/24:

  • Begin preparation for milling at Val-de-mere Ave, Twin Brooks Park, Rocky Ridge Dr, Beech Tree Cir, Blueberry Rd, Berry Ln. 
  • Fog Sealing Road Treatment to begin on Bayberry Ln,  Sunny Ridge Pkwy, Rebecca St, Lindberg Dr, Forest View St, Rempsen St, Cottage Pl, Anthony Pl, Chalon Rd, Wildfire Ln, Barnswallow Dr, Nuthatch Rd, North Green Acres Ln, Marathon Rd, Green Acres 
  • Drainage repairs to continue on Country Ln, Deerfield Dr, Elaine Pl, Four Seasons Ln, Ivywood Pl and Leonard Pl

Week of 8/12/24:

  • Milling at Val-de-mere Ave, Twin Brooks Park, Rocky Ridge Dr, Beech Tree Cir, Blueberry Rd, Berry Ln.
  • Fog Sealing Road Treatment to continue on Bayberry Ln,  Sunny Ridge Pkwy, Rebecca St, Lindberg Dr, Forest View St, Rempsen St, Cottage Pl, Anthony Pl, Chalon Rd, Wildfire Ln, Barnswallow Dr, Nuthatch Rd, North Green Acres Ln, Marathon Rd, Green Acres 
  • Drainage repairs to continue on Country Ln, Deerfield Dr, Elaine Pl, Four Seasons Ln, Ivywood Pl and Leonard Pl

7/15/24: 2 Week Look Ahead

Week of 7/15/24:

  • Drainage repairs to continue on Country Ln, Deerfield Dr, Elaine Pl, Four Seasons Ln, Ivywood Pl, Koger Rd, Leonard Pl, Merwin St,       Raynor Ave, and Raynor Pl
  • Continue driveway apron repair and handwork on Gisella Rd, Clearwater Ln, Hemlock Trail, Bear Den Road, Blue Ridge Drive and Pinewood Trail
  • Chip Sealing Pavement Treatment to begin on the following roads: Bayberry Ln,  Sunny Ridge Pkwy, Rebecca St, Lindberg Dr, Forest View St, Rempsen St, Cottage Pl, Anthony Pl, Chalon Rd, Wildfire Ln, Barnswallow Dr, Nuthatch Rd, North Green Acres Ln, Marathon Rd, Green Acres 

Week of 7/22/24:

  • Drainage repairs to continue on Country Ln, Deerfield Dr, Elaine Pl, Four Seasons Ln, Ivywood Pl, Koger Rd, Leonard Pl, Merwin St,        Raynor Ave, and Raynor Pl
  • Chip Sealing Pavement Treatment to continue on the following roads: Bayberry Ln,  Sunny Ridge Pkwy, Rebecca St, Lindberg Dr, Forest View St, Rempsen St, Cottage Pl, Anthony Pl, Chalon Rd, Wildfire Ln, Barnswallow Dr, Nuthatch Rd, North Green Acres Ln, Marathon Rd,  and Green Acres Ln

7/1/24: 2 Week Look Ahead

Week of 7/1/24:

  • Drainage repairs to continue on Country Ln, Deerfield Dr, Elaine Pl, Four Seasons Ln, Ivywood Pl, Koger Rd, Leonard Pl, Merwin St, Raynor Ave, and Raynor Pl
  • Continue paving on Gisella Rd, Clearwater Ln, Hemlock Trail, Bear Den Road, Blue Ridge Drive and Pinewood Trail
  • Begin driveway apron repair and handwork on Gisella Rd, Clearwater Ln, Hemlock Trail, Bear Den Road, Blue Ridge Drive and Pinewood Trail

Week of 7/8/24:

  • Drainage repairs to continue on Country Ln, Deerfield Dr, Elaine Pl, Four Seasons Ln, Ivywood Pl, Koger Rd, Leonard Pl, Merwin St, Raynor Ave, and Raynor Pl
  • Continue driveway apron repair and handwork on Gisella Rd, Clearwater Ln, Hemlock Trail, Bear Den Road, Blue Ridge Drive and Pinewood Trail

6/10/24: 2 Week Look Ahead

Week of 6/10/24:

  • Drainage repairs to begin on Country Ln, Deerfield Dr, Elaine Pl, Four Seasons Ln, Ivywood Pl, Koger Rd, Leonard Pl, Merwin St, Raynor Ave, and Raynor Pl
  • Driveway apron repair and handwork to begin on Francis Street, Killian Ave, Parkway Dr, Plumb Rd, Plymouth Ave, Candlewood Rd, Rosemond Terr and Samuel Street

Week of 6/17/24:

  • Drainage repairs to continue on Country Ln, Deerfield Dr, Elaine Pl, Four Seasons Ln, Ivywood Pl, Koger Rd, Leonard Pl, Merwin St, Raynor Ave, and Raynor Pl
  • Driveway apron repair and handwork to continue on Francis Street, Killian Ave, Parkway Dr, Plumb Rd, Plymouth Ave, Candlewood Rd, Rosemond Terr and Samuel Street
  • Milling and Paving to begin on Gisella Rd, Clearwater Ln, Hemlock Trail, Bear Den Road, Blue Ridge Drive and Pinewood Trail

5/30/24: 2 Week Look Ahead

Week of 5/27/24:

  • Continue drainage repairs on Blueberry Road
  • Continue paving on Francis Street, Killian Ave, Parkway Dr, Plumb Rd, Plymouth Ave, Candlewood Rd, Rosemond Terr and Samuel Street

Week of 6/03/24:

  • Continue drainage repairs on Blueberry Road
  • Continue paving on Francis Street, Killian Ave, Parkway Dr, Plumb Rd, Plymouth Ave, Candlewood Rd, Rosemond Terr and Samuel Street

5/10/24: 2 Week Look Ahead

Week of 5/13/24:

  • Continue paving Elmstead Road, Hampton Road, Histon Road, Johnson Street, Kingston Road, Mitchell Road, and Sherman Avenue

Week of 5/20/24:

  • Begin milling at Francis St, Killian Ave, Parkway Dr, Plumb Rd, Plymouth Ave, Candlewood Rd, Rosemond Ter, Samuel St, Clearwater Ln

4/17/24: 2 Week Look Ahead

Week of 4/22:

  • Begin drainage repairs on Rocky Ridge Drive
  • Begin milling Elmstead Road, Hampton Road, Histon Road, Johnson Street, Kingston Road, Mitchell Road, and Sherman Avenue

 Week of 4/29:

  • Continue drainage repairs on Rocky Ridge Drive
  • Begin paving Elmstead Road, Hampton Road, Histon Road, Johnson Street, Kingston Road, Mitchell Road, and Sherman Avenue

10/16/23 Update

  • Paving work has been completed for the 2023 paving season. Miscellaneous landscaping work will continue through the end of October.  

9/18/23: 2 Week Look Ahead

Week of 9/18:

  • Paving and handwork at Catherine St (N), Clark Rd, Walker Rd, Mulberry St, Ascolese Rd, part of Sterling Rd, Bittersweet Ln, Grove St, Wilmot Ave, Garden St, Orchard St, Birch St, Chestnut St, Fairchild Rd, Fairchild Cir, Brewster Pl. 

 Week of 9/25:

  • Paving and handwork at Catherine St (N), Clark Rd, Walker Rd, Mulberry St, Ascolese Rd, part of Sterling Rd, Bittersweet Ln, Grove St, Wilmot Ave, Garden St, Orchard St, Birch St, Chestnut St, Fairchild Rd, Fairchild Cir, Brewster Pl.

9/5/23: 2 Week Look Ahead

Week of 9/5:

  • Begin milling at Mulberry St, Ascolese Rd, Sterling Rd, Bittersweet Ln, Catherine St, Devellis Dr. 
  • Continue paving at Grove St, Wilmot Ave, Garden St, Orchard St, Birch St, Chestnut St, Fairchild Rd, Fairchild Cir, Brewster Pl. 

 Week of 9/11:

  • Begin paving at Mulberry St, Ascolese Rd, Sterling Rd, Bittersweet Ln, Catherine St, Devellis Dr. 

8/21/23: 2 Week Look Ahead

Week of 8/21:

  • Continue prep work and begin paving at Grove St, Wilmot Ave, Garden St, Orchard St, Birch St, Chestnut St, Fairchild Rd, Fairchild Cir, Brewster Pl. 

 Week of 8/28:

  • Paving at Grove St, Wilmot Ave, Garden St, Orchard St, Birch St, Chestnut St, Fairchild Rd, Fairchild Cir, Brewster Pl 
  • Begin preparation for milling at Mulberry St, Ascolese Rd, Sterling Rd, Bittersweet Ln, Catherine St, Devellis Dr. 

8/07/23: 2 Week Look Ahead

Week of August 7, 2023:

  • Begin milling at Grove St, Wilmot Ave, Garden St, Orchard St, Birch St, Chestnut St, Fairchild Rd, Fairchild Cir, Brewster Pl.

 Week of August 14, 2023:

  • Patching & clean-up in preparation for paving at Grove St, Wilmot Ave, Garden St, Orchard St, Birch St, Chestnut St, Fairchild Rd, Fairchild Cir, Brewster Pl 

7/24/23: 2 Week Look Ahead

Week of July 24, 2023

  • Paving at Edmond St, Shady Ln, Wood Ave, Catherine St, Clark Rd, Devellis Dr, Walker Rd, Lullwater Rd, portions of Sterling Rd and Edmond St.
  • Begin preparation for milling at Grove St, Wilmot Ave, Garden St, Orchard St, Birch St, Chestnut St, Fairchild Rd, Fairchild Cir, Brewster Pl. 

 Week of July 31, 2023:

  • Paving & handwork at Edmond St, Shady Ln, Wood Ave, Catherine St, Clark Rd, Devellis Dr, Walker Rd, Lullwater Rd, portions of Sterling Rd and Edmond St.

7/10/23: 2 Week Look Ahead

Week of July 10, 2023:

  • Paving binder at Edmond St, Shady Ln, Wood Ave.
  • Begin milling on Madison Ave, Catherine St, Clark Rd, Devellis Dr, Walker Rd, Lullwater Rd, portions of Sterling Rd and Edmond St.  

Week of July 17, 2023:

  • Install curbing at Edmond St, Shady Ln, Wood Ave.

6/26/23: 2 Week Look Ahead

Week of June 26, 2023:

  • Reclaiming, grading and begin paving at Edmond St, Lullwater Rd, Shady Ln, Wood Ave.

Week of July 3, 2023:

  • Continue paving, install curbing at Edmond St, Lullwater Rd, Shady Ln, Wood Ave.
  • Begin preparation for milling at Madison Ave, Devellis Dr, Lullwater Rd, Catherine St, Walker Rd, Clark Rd, portion of Sterling Rd. 


6/20/23: 2 Week Look Ahead

Week of June 20, 2023:

  • Reclaiming and grading at Edmond St, Lullwater Rd, Shady Ln, Wood Ave.

Week of June 26, 2023:

  • Reclaiming, grading and begin paving at Edmond St, Lullwater Rd, Shady Ln, Wood Ave.

6/5/23: 2 Week Look Ahead

Week of  June 5, 2023:

  • Continue drainage repairs to prepare for paving 

Week of  June 12, 2023:

  • Preparation for reclaiming at Edmond St, Lullwater Rd, Shady Ln, Wood Ave.

5/26/23: 2 Week Look Ahead

Week of  May 29, 2023:

  • Handwork at Colony Ave, Inwood Dr, Springwood Dr, Old Elm Rd
  • Pavement Preservation to continue Town-wide

 Week of  June 5, 2023:

  • Continue drainage repairs to prepare for paving 

5/22/23: 2 Week Look Ahead

Week of  May 22, 2023:

  • Paving at Colony Ave, Inwood Dr, Springwood Dr, Old Elm Rd
  • Pavement Preservation to continue Town-wide

Week of  May 29, 2023:

  • Pavement Preservation to continue Town-wide

5/15/23: 2 Week Look Ahead

Week of  May 15, 2023:

  • Milling to begin at Colony Ave, Inwood Dr, Springwood Dr, Old Elm Rd
  • Pavement Preservation to continue Town-wide

Week of May 22, 2023:

  • Pavement Preservation to continue Town-wide

9/02/22: 2 Week Look Ahead

Week of September 5th, 2022:

  • Continue Drainage work on Oldfield Rd & Beacon Hill Rd

Week of September 12th, 2022:

  • Continue Drainage work on Oldfield Rd, Beacon Hill Rd, and Pilgrim Lane

Begin milling Jog Hill Road and Oldfield Road between Chalon Road and Beacon Hill Rd in preparation for pavingJune

8/19/22: 2 Week Look Ahead

Week of August 22nd, 2022:

  • Landscaping & miscellaneous paving work on Williams Road between Leonard Place and Deerfield Drive. 
  • Continue Drainage work on Oldfield Rd & Beacon Hill Rd
  • Sidewalk installation from Blue Ridge Drive to Booth Hill School

Week of August 29th, 2022:

  • Landscaping & miscellaneous paving work on Williams Road between Leonard Place and Deerfield Drive. 
  • Continue Drainage work on Oldfield Rd & Beacon Hill Rd
  • Sidewalk installation from Blue Ridge Drive to Booth Hill School

8/15/22: 2 Week Look Ahead

Week of August 15th, 2022:

  • Landscaping & miscellaneous paving work on Williams Road between Leonard Place and Deerfield Drive. 
  • Drainage work on Oldfield Rd & Beacon Hill Rd

Week of August 22nd, 2022:

  • Landscaping & miscellaneous paving work on Williams Road between Leonard Place and Deerfield Drive. 
  • Drainage work on Oldfield Rd & Beacon Hill Rd

8/08/22: 2 Week Look Ahead

Week of August 8th, 2022:

  • Finish miscellaneous paving work and begin landscaping on Williams Road between Leonard Place and Deerfield Drive.  

Week of August 15th, 2022:

  • Finish landscaping on Williams Road between Leonard Place and Deerfield Drive. 

8/01/22: 2 Week Look Ahead

Week of August 1st, 2022:

  • Continue miscellaneous paving work on Williams Road between Leonard Place and Deerfield Drive. 

Week of August 8th, 2022:

  • Finish paving, handwork & curbing, on Williams Road between Leonard Place and Deerfield Drive. 

7/25/22: 2 Week Look Ahead

Week of July 25th, 2022:

  • Finish paving, begin handwork & curbing, on Williams Road between Leonard Place and Deerfield Drive 
  • Continue cracksealing of Booth Hill Road, Stonehouse Road and Madison Ave between Buck Hill Road and Canoe Brook Road

 Week of August 1st, 2022:

  • Finish paving, handwork & curbing, on Williams Road between Leonard Place and Deerfield Drive. 

7/17/22: 2 Week Look Ahead

Week of July 18th, 2022:

  • Begin paving on Williams Road between Leonard Place and Deerfield Drive 
  • Continue cracksealing of Booth Hill Road, Stonehouse Road and Madison Ave between Buck Hill Road and Canoe Brook Road 

Week of July 25th, 2022

  • Finish paving, begin handwork & curbing, on Williams Road between Leonard Place and Deerfield Drive 
  • Continue cracksealing of Booth Hill Road, Stonehouse Road and Madison Ave between Buck Hill Road and Canoe Brook Road

7/5/22: 2 Week Look Ahead

Week of July 4thth, 2022:

  • Continue paving on Madison Ave between Canoe Brook Road and Chestnut Hill Road
  • Continue Drainage Repairs on Jog Hill Road
  • Preparation for reclaiming of Williams Road between Leonard Place and Deerfield Drive 

Week of July 11th, 2022

  • Begin Drainage Repairs on Beacon Hill Road and Pilgrim Lane
  • Begin reclaiming of Williams Road between Leonard Place and Deerfield Drive
  • Begin cracksealing of Booth Hill Road, Stonehouse Road and Madison Ave between Buck Hill Road and Canoe Brook Road

6/24/22: 2 Week Look Ahead

Week of June 27th, 2022:

  • Begin paving on Madison Ave between Canoe Brook Road and Chestnut Hill Road
  • Begin paving on Lorma Ave and Smith Place
  • Continue Drainage Repairs on Jog Hill Road

Week of July 4th, 2022

  • Continue paving on Madison Ave between Canoe Brook Road and Chestnut Hill Road
  • Continue paving on Lorma Ave and Smith Place
  • Continue Drainage Repairs on Jog Hill Road
  • Preparation for milling of Williams Road between Leonard Place and Frenchtown Road

6/21/22: 2 Week Look Ahead

Week of June 20th, 2022:

  • Begin milling on Madison Ave between Canoe Brook Road and Chestnut Hill Road
  • Begin Drainage Repairs on Jog Hill Road

Week of June 27th, 2022

  • Continue milling on Madison Ave between Canoe Brook Road and Chestnut Hill Road
  • Continue Drainage Repairs on Jog Hill Road

5/16/22: 2 Week Look Ahead

Week of May 16th, 2022:

  • Begin milling on Chatham Dr, Cardinal Cir and Midland Rd
  • Continue drainage repairs on Madison Ave up to Chestnut Hill Road

Week of May 23rd, 2022

  • Continue milling Chatham Dr, Cardinal Circle, and Midland Road in preparation for paving
  • Continue drainage repairs on Madison Ave up to Chestnut Hill Road

5/6/21: 2 Week Look Ahead

Week of May 16th, 2022:

  • Begin milling on Chatham Dr, Cardinal Cir and Midland Rd

11/29/2021

  • Winter Shutdown is in effect until further notice

11/18/21: 2 Week Look Ahead

Week of November 22nd , 2021:

  • Continue drainage repairs on Williams Road

Week of  November 29thth , 2021:

  • Continue drainage repairs on Williams Road

9/09/21: 2 Week Look Ahead

Week of September 13th , 2021:

  • Continue paving and begin driveway and curb restoration on Great Neck Road, Laurie Road, Woodmere Drive and Fawn Circle 
  • Begin milling on Botsford Place, Ochsner Place and Gorham Place

Week of  September 20th , 2021:

  • Continue driveway and curb restoration on Great Neck Road, Laurie Road, Woodmere Drive and Fawn Circle 
  • Begin paving on Botsford Place, Ochsner Place and Gorham Place

8/09/21: 2 Week Look Ahead

Week of August 9th , 2021:

  • Begin milling of Shelton Road
  • Begin milling various sections of Daniels Farm Road between Daniels Farm School and Wareham Place
  • Begin milling Great Neck Road, Laurie Road, Woodmere Drive and Fawn Circle
  • Begin drainage repairs on Botsford Place, Ochsner Place and Gorham Place

Week of  August 16th , 2021:

  • Begin paving of Shelton Road
  • Begin paving various sections of Daniels Farm Road between Daniels Farm School and Wareham Place
  • Begin paving Great Neck Road, Laurie Road, Woodmere and Fawn Circle
  • Continue drainage repairs on Botsford Place, Ochsner Place and Gorham Place

6/16/21: 2 Week Look Ahead

Week of June 21st , 2021:

  • Begin milling of Canoe Brook Rd, Anita Ave, Claire Place, Rosellen Dr and Madison Ave from Station Hill to Buck Hill Road

Week of  June 28th , 2021:

  • Continue milling of Canoe Brook Rd, Anita Ave, Claire Place, Rosellen Dr and Madison Ave from Station Hill to Buck Hill Road
  • Begin paving binder course of Canoe Brook Rd, Anita Ave, Claire Place, Rosellen Dr and Madison Ave from Station Hill to Buck Hill Road 

4/16/21: 2 Week Look Ahead

Week of April 19th , 2021:

  • Begin reclaiming of Glenbrook Road, Aragon Drive and Rangely Drive
  • Drainage repairs to continue on Teller Road, Beach Hill Road and Stirrup Drive

Week of  April 26th , 2021:

  • Continue reclaiming of Glenbrook Road, Aragon Drive and Rangely Drive
  • Begin paving of Glenbrook Road, Aragon Drive and Rangely Drive 
  • Drainage repairs to continue on Teller Road, Beach Hill Road and Stirrup Drive

8/19/20: 2 Week Look Ahead

Week of August 17th , 2020:

  • Paving top course of Old Dike Road and Dale Road
  • Drainage repairs to continue on Wordins Lane
  • Landscaping of Merrill Road, Chatfield Drive, Elmwood Road, Green Street and Walnut Ave

Week of August 24th , 2020:

  • Milling to begin on Abric Drive, Bonheur Road, Campbell Road, Fieldstone Court, Gaylord Road, Hitching Post Lane, Leighton Road, Plattsville Road, Richfield Road, Shelbourne Road and Winslow Road
  • Paving to continue on Dale Road
  • Driveway apron repairs on Old Dike Road and Dale Road
  • Drainage repairs to continue on Wordins Lane

7/28/20: 2 Week Look Ahead

Week of July 27th , 2020:

  • Paving of driveway aprons and hand work to begin on  Green St, Walnut Ave, Elmwood Ave, Merrill Road, Chatfield Drive, Maymount Lane, Dayton Circle and Dale Road
  • Continue drainage repairs on Winslow Road, Leighton Road, Gaylord Road and Shelbourne Road
  • Milling of Old Dike Road to begin

Week of August 3rd , 2020:

  • Paving of driveway aprons and hand work to continue on  Green St, Walnut Ave, Elmwood Ave, Merrill Road, Chatfield Drive, Maymount Lane, Dayton Circle and Dale Road
  • Continue drainage repairs on Winslow Road, Leighton Road, Gaylord Road and Shelbourne Road
  • Milling of Old Dike Road to continue

7/15/20: 2 Week Look Ahead

Week of July 13th , 2020:

  • Begin installing curbing on Green St, Walnut Ave, Elmwood Ave, Merrill Road, Maymount Lane, Dayton Circle, Dale Road, Glenbrook Road, Rangely Drive and Aragon Drive
  • Continue drainage repairs on Winslow Road, Leighton Road, Gaylord Road and Shelbourne Road

Week of July 20th , 2020:

  • Continue installing curbing on Green St, Walnut Ave, Elmwood Ave, Merrill Road, Maymount Lane, Dayton Circle, Dale Road, Glenbrook Road, Rangely Drive and Aragon Drive
  • Begin paving top course on Green St, Walnut Ave, Elmwood Ave, Merrill Road, Maymount Lane, Dayton Circle, Dale Road, Glenbrook Road, Rangely Drive and Aragon Drive
  • Drainage repairs to continue on Winslow Road, Leighton Road, Gaylord Road and Shelbourne Road

6/22/20: 2 Week Look Ahead

Week of June 22nd , 2020:

  • Begin paving binder course on Green St, Walnut Ave, Elmwood Ave and Merrill Road
  • Reclaiming of roadway to begin on Maymount Lane, Dayton Circle, Dale Road, Glenbrook Road, Rangely Drive and Aragon Drive
  • Drainage repairs to continue on Glenbrook Road
  • Drainage repairs to begin on Winslow Road, Leighton Road, Gaylord Road, Shelbourne Road and Hitching Post Lane

Week of June 29th , 2020:

  • Continue paving binder course on Green St, Walnut Ave, Elmwood Ave and Merrill Road
  • Reclaiming of roadway to continue on Maymount Ln, Dayton Circle, Dale Road, Glenbrook Road, Rangely Drive and Aragon Drive
  • Repairs to driveway aprons on Green St, Walnut Ave, Elmwood Ave and Merrill Road
  • Drainage repairs to continue on Winslow Road, Leighton Road, Gaylord Road, Shelbourne Road and Hitching Post Lane

6/16/20: 2 Week Look Ahead

Week of June 15th , 2020:

  • Drainage repairs to continue on Merrill Road and Chatfield Drive
  • Removal of curbs on Green St, Walnut Ave, Elmwood Ave and Merrill Road
  • Reclaiming of roadway to begin on Green St, Walnut Ave, Elmwood Ave and Merrill Road
  • Drainage repairs to begin on Glenbrook Road

Week of June 22nd , 2020:

  • Drainage repairs to continue on Glenbrook Road
  • Reclaiming of roadway to continue on Green St, Walnut Ave, Elmwood Ave and Merrill Road
  • Repairs to driveway aprons on Green St, Walnut Ave, Elmwood Ave and Merrill Road

5/11/20: 2 Week Look Ahead

Week of May 11th , 2020:

  • Saw-cutting of asphalt to begin on Merrill Road and Chatfield Drive
  • Drainage repairs to begin on Merrill Road and Chatfield Drive

Week of May 18th , 2020:

  • Drainage repairs to continue on Merrill Road and Chatfield Drive

4/01/20: 2 Week Look Ahead

Week of March 30th , 2020:

  • Drainage repairs to begin on Maymount Lane and Dale Road

Week of April 6th , 2020:

  • Drainage repairs to continue on Maymount Lane and Dale Road

1/10/2020: 2 Week Look Ahead


Winter Shutdown is in effect until further notice

12/20/2019: 2 Week Look Ahead

Week of December 23rd , 2019:

  • Drainage Repairs to continue on Madison Ave between Tashua Road and Newton Lane

Week of December 30th , 2019:

  • Drainage repairs have been completed on Madison Ave between Tahsua Road and Newton Lane

12/13/2019: 2 Week Look Ahead

Week of December 16th , 2019:

  • Drainage Repairs to continue on Madison Ave between Tashua Road and Newton Lane

Week of December 23rd , 2019:

  • Drainage repairs to continue on Madison Ave between Tashua Road and Newton Lane

12/06/2019: 2 Week Look Ahead

Week of December 9th , 2019:

  1. Drainage repairs to continue on Campbell Road and Richfield Road

  2. Drainage Repairs to begin on Madison Ave between Tashua Road and Newton Lane

Week of December 16th , 2019:

  1. Drainage repairs to continue on Madison Ave between Tashua Road and Newton Lane

11/27/19: 2 Week Look Ahead

Week of December 2nd , 2019:

  • Drainage repairs to continue on Campbell Road and Richfield Road

Week of December 9th , 2019:

  • Drainage repairs to continue on Campbell Road and Richfield Road

11/22/19: 2 Week Look Ahead

Week of November 25th , 2019:

  • Drainage repairs to continue on Campbell Road and Richfield Road

Week of December 2nd , 2019:

  • Drainage repairs to continue on Campbell Road and Richfield Road

11/15/19: 2 Week Look Ahead

Week of November 18th , 2019:

  • Drainage repairs to continue on Elmwood and Walnut Avenue 

Week of November 25th , 2019:

  • Drainage repairs to continue on Elmwood and Walnut Avenue
  • Drainage repairs to begin on Campbell Road and Richfield Road

11/08/19: 2 Week Look Ahead

Week of November 11th , 2019:

  • Drainage repairs to continue on Elmwood and Walnut Avenue

Week of November 18th , 2019:

  • Drainage repairs to continue on Elmwood and Walnut Avenue
  • Drainage repairs to begin on Campbell Road and Richfield Road

11/01/19: 2 Week Look Ahead

Week of November 4th , 2019:

  • Drainage repairs to continue on Elmwood and Walnut Avenue 

Week of November 11th , 2019:

  • Drainage repairs to continue on Elmwood and Walnut Avenue

10/25/19: 2 Week Look Ahead

Week of October 28th , 2019:

  • Drainage repairs to continue on Abric Drive, Green Street, and Bonheur Road
  • Drainage repairs to begin on Elmwood and Walnut Avenue 

Week of November 4th , 2019:

  • Drainage repairs to continue on Elmwood and Walnut Avenue

10/18/2019: 2 Week Look Ahead

Week of October 21st , 2019:

  1. Drainage repairs to continue on Abric Drive, Green Street, and Bonheur Road
  2. Drainage repairs to begin on Elmwood and Walnut Avenue

Week of October 28th , 2019:

  1. Drainage repairs to continue on Abric Drive, Green Street, and Bonheur Road
  2. Drainage repairs to continue on Elmwood and Walnut Avenue

9/27/19: 2 Week Look Ahead

Week of September 30rd, 2019:

1.    Drainage repairs to continue on Old Dike Road

2.    Landscaping and repairs to driveway aprons to begin on Woodridge Circle and Judson Street

3.    Landscaping and repairs to driveway aprons to begin on Rocky Hill Rd and Rocky Hill Terrace

4.    Drainage repairs to begin on Abric Drive, Green Street, and Bonheur Road

Week of October 7th, 2019:

1.    Landscaping and repairs to driveway aprons to begin on Woodridge Circle and Judson Street

2.    Landscaping and repairs to driveway aprons to begin on Rocky Hill Rd and Rocky Hill Terrace

3.    Drainage repairs to begin on Abric Drive, Green Street, and Bonheur Road