- Home
- Government
- Departments M - S
- Public Works
- DPW Projects
- Road Paving Program
Road Paving Program
Project Description
The Town of Trumbull Road Paving Program is dedicated to repairing various roads surface and subsurface infrastructure. This includes repairs to the drainage and sanitary systems that have been previously inspected.
Various sections of the road will be closed to through traffic at different times throughout this process. The Town of Trumbull will endeavor to keep disturbance to a minimum. However, your patience will be much appreciated. Construction work is anticipated to start at 7:00 AM daily. All bus stops will remain at their current locations.
Pavement Condition Index Map
2021 Pavement Condition Index Map (PDF): The Pavement Condition ratings will be updated annually, upon completion of each paving season.
Project Progress
The Town will post updates to this website and include the anticipated two week look ahead for the project. Dates and locations are subject to change if unforeseen factors arise.
9/18/23: 2 Week Look Ahead
Week of 9/18:
- Paving and handwork at Catherine St (N), Clark Rd, Walker Rd, Mulberry St, Ascolese Rd, part of Sterling Rd, Bittersweet Ln, Grove St, Wilmot Ave, Garden St, Orchard St, Birch St, Chestnut St, Fairchild Rd, Fairchild Cir, Brewster Pl.
Week of 9/25:
- Paving and handwork at Catherine St (N), Clark Rd, Walker Rd, Mulberry St, Ascolese Rd, part of Sterling Rd, Bittersweet Ln, Grove St, Wilmot Ave, Garden St, Orchard St, Birch St, Chestnut St, Fairchild Rd, Fairchild Cir, Brewster Pl.
9/5/23: 2 Week Look Ahead
Week of 9/5:
- Begin milling at Mulberry St, Ascolese Rd, Sterling Rd, Bittersweet Ln, Catherine St, Devellis Dr.
- Continue paving at Grove St, Wilmot Ave, Garden St, Orchard St, Birch St, Chestnut St, Fairchild Rd, Fairchild Cir, Brewster Pl.
Week of 9/11:
- Begin paving at Mulberry St, Ascolese Rd, Sterling Rd, Bittersweet Ln, Catherine St, Devellis Dr.
8/21/23: 2 Week Look Ahead
Week of 8/21:
- Continue prep work and begin paving at Grove St, Wilmot Ave, Garden St, Orchard St, Birch St, Chestnut St, Fairchild Rd, Fairchild Cir, Brewster Pl.
Week of 8/28:
- Paving at Grove St, Wilmot Ave, Garden St, Orchard St, Birch St, Chestnut St, Fairchild Rd, Fairchild Cir, Brewster Pl
- Begin preparation for milling at Mulberry St, Ascolese Rd, Sterling Rd, Bittersweet Ln, Catherine St, Devellis Dr.
8/07/23: 2 Week Look Ahead
Week of August 7, 2023:
- Begin milling at Grove St, Wilmot Ave, Garden St, Orchard St, Birch St, Chestnut St, Fairchild Rd, Fairchild Cir, Brewster Pl.
Week of August 14, 2023:
- Patching & clean-up in preparation for paving at Grove St, Wilmot Ave, Garden St, Orchard St, Birch St, Chestnut St, Fairchild Rd, Fairchild Cir, Brewster Pl
7/24/23: 2 Week Look Ahead
Week of July 24, 2023
- Paving at Edmond St, Shady Ln, Wood Ave, Catherine St, Clark Rd, Devellis Dr, Walker Rd, Lullwater Rd, portions of Sterling Rd and Edmond St.
- Begin preparation for milling at Grove St, Wilmot Ave, Garden St, Orchard St, Birch St, Chestnut St, Fairchild Rd, Fairchild Cir, Brewster Pl.
Week of July 31, 2023:
- Paving & handwork at Edmond St, Shady Ln, Wood Ave, Catherine St, Clark Rd, Devellis Dr, Walker Rd, Lullwater Rd, portions of Sterling Rd and Edmond St.
7/10/23: 2 Week Look Ahead
Week of July 10, 2023:
- Paving binder at Edmond St, Shady Ln, Wood Ave.
- Begin milling on Madison Ave, Catherine St, Clark Rd, Devellis Dr, Walker Rd, Lullwater Rd, portions of Sterling Rd and Edmond St.
Week of July 17, 2023:
- Install curbing at Edmond St, Shady Ln, Wood Ave.
6/26/23: 2 Week Look Ahead
Week of June 26, 2023:
- Reclaiming, grading and begin paving at Edmond St, Lullwater Rd, Shady Ln, Wood Ave.
Week of July 3, 2023:
- Continue paving, install curbing at Edmond St, Lullwater Rd, Shady Ln, Wood Ave.
- Begin preparation for milling at Madison Ave, Devellis Dr, Lullwater Rd, Catherine St, Walker Rd, Clark Rd, portion of Sterling Rd.
6/20/23: 2 Week Look Ahead
Week of June 20, 2023:
- Reclaiming and grading at Edmond St, Lullwater Rd, Shady Ln, Wood Ave.
Week of June 26, 2023:
- Reclaiming, grading and begin paving at Edmond St, Lullwater Rd, Shady Ln, Wood Ave.
6/5/23: 2 Week Look Ahead
Week of June 5, 2023:
- Continue drainage repairs to prepare for paving
Week of June 12, 2023:
- Preparation for reclaiming at Edmond St, Lullwater Rd, Shady Ln, Wood Ave.
5/26/23: 2 Week Look Ahead
Week of May 29, 2023:
- Handwork at Colony Ave, Inwood Dr, Springwood Dr, Old Elm Rd
- Pavement Preservation to continue Town-wide
Week of June 5, 2023:
- Continue drainage repairs to prepare for paving
5/22/23: 2 Week Look Ahead
Week of May 22, 2023:
- Paving at Colony Ave, Inwood Dr, Springwood Dr, Old Elm Rd
- Pavement Preservation to continue Town-wide
Week of May 29, 2023:
- Pavement Preservation to continue Town-wide
5/15/23: 2 Week Look Ahead
Week of May 15, 2023:
- Milling to begin at Colony Ave, Inwood Dr, Springwood Dr, Old Elm Rd
- Pavement Preservation to continue Town-wide
Week of May 22, 2023:
- Pavement Preservation to continue Town-wide
9/02/22: 2 Week Look Ahead
Week of September 5th, 2022:
- Continue Drainage work on Oldfield Rd & Beacon Hill Rd
Week of September 12th, 2022:
- Continue Drainage work on Oldfield Rd, Beacon Hill Rd, and Pilgrim Lane
- Begin milling Jog Hill Road and Oldfield Road between Chalon Road and Beacon Hill Rd in preparation for pavingJune
8/19/22: 2 Week Look Ahead
Week of August 22nd, 2022:
- Landscaping & miscellaneous paving work on Williams Road between Leonard Place and Deerfield Drive.
- Continue Drainage work on Oldfield Rd & Beacon Hill Rd
- Sidewalk installation from Blue Ridge Drive to Booth Hill School
Week of August 29th, 2022:
- Landscaping & miscellaneous paving work on Williams Road between Leonard Place and Deerfield Drive.
- Continue Drainage work on Oldfield Rd & Beacon Hill Rd
- Sidewalk installation from Blue Ridge Drive to Booth Hill School
8/15/22: 2 Week Look Ahead
Week of August 15th, 2022:
- Landscaping & miscellaneous paving work on Williams Road between Leonard Place and Deerfield Drive.
- Drainage work on Oldfield Rd & Beacon Hill Rd
Week of August 22nd, 2022:
- Landscaping & miscellaneous paving work on Williams Road between Leonard Place and Deerfield Drive.
- Drainage work on Oldfield Rd & Beacon Hill Rd
8/08/22: 2 Week Look Ahead
Week of August 8th, 2022:
- Finish miscellaneous paving work and begin landscaping on Williams Road between Leonard Place and Deerfield Drive.
Week of August 15th, 2022:
- Finish landscaping on Williams Road between Leonard Place and Deerfield Drive.
8/01/22: 2 Week Look Ahead
Week of August 1st, 2022:
- Continue miscellaneous paving work on Williams Road between Leonard Place and Deerfield Drive.
Week of August 8th, 2022:
- Finish paving, handwork & curbing, on Williams Road between Leonard Place and Deerfield Drive.
7/25/22: 2 Week Look Ahead
Week of July 25th, 2022:
- Finish paving, begin handwork & curbing, on Williams Road between Leonard Place and Deerfield Drive
- Continue cracksealing of Booth Hill Road, Stonehouse Road and Madison Ave between Buck Hill Road and Canoe Brook Road
Week of August 1st, 2022:
- Finish paving, handwork & curbing, on Williams Road between Leonard Place and Deerfield Drive.
7/17/22: 2 Week Look Ahead
Week of July 18th, 2022:
- Begin paving on Williams Road between Leonard Place and Deerfield Drive
- Continue cracksealing of Booth Hill Road, Stonehouse Road and Madison Ave between Buck Hill Road and Canoe Brook Road
Week of July 25th, 2022
- Finish paving, begin handwork & curbing, on Williams Road between Leonard Place and Deerfield Drive
- Continue cracksealing of Booth Hill Road, Stonehouse Road and Madison Ave between Buck Hill Road and Canoe Brook Road
7/5/22: 2 Week Look Ahead
Week of July 4thth, 2022:
- Continue paving on Madison Ave between Canoe Brook Road and Chestnut Hill Road
- Continue Drainage Repairs on Jog Hill Road
- Preparation for reclaiming of Williams Road between Leonard Place and Deerfield Drive
Week of July 11th, 2022
- Begin Drainage Repairs on Beacon Hill Road and Pilgrim Lane
- Begin reclaiming of Williams Road between Leonard Place and Deerfield Drive
- Begin cracksealing of Booth Hill Road, Stonehouse Road and Madison Ave between Buck Hill Road and Canoe Brook Road
6/24/22: 2 Week Look Ahead
Week of June 27th, 2022:
- Begin paving on Madison Ave between Canoe Brook Road and Chestnut Hill Road
- Begin paving on Lorma Ave and Smith Place
- Continue Drainage Repairs on Jog Hill Road
Week of July 4th, 2022
- Continue paving on Madison Ave between Canoe Brook Road and Chestnut Hill Road
- Continue paving on Lorma Ave and Smith Place
- Continue Drainage Repairs on Jog Hill Road
- Preparation for milling of Williams Road between Leonard Place and Frenchtown Road
6/21/22: 2 Week Look Ahead
Week of June 20th, 2022:
- Begin milling on Madison Ave between Canoe Brook Road and Chestnut Hill Road
- Begin Drainage Repairs on Jog Hill Road
Week of June 27th, 2022
- Continue milling on Madison Ave between Canoe Brook Road and Chestnut Hill Road
- Continue Drainage Repairs on Jog Hill Road
5/16/22: 2 Week Look Ahead
Week of May 16th, 2022:
- Begin milling on Chatham Dr, Cardinal Cir and Midland Rd
- Continue drainage repairs on Madison Ave up to Chestnut Hill Road
Week of May 23rd, 2022
- Continue milling Chatham Dr, Cardinal Circle, and Midland Road in preparation for paving
- Continue drainage repairs on Madison Ave up to Chestnut Hill Road
5/6/21: 2 Week Look Ahead
Week of May 16th, 2022:
- Begin milling on Chatham Dr, Cardinal Cir and Midland Rd
11/29/2021
- Winter Shutdown is in effect until further notice
11/18/21: 2 Week Look Ahead
Week of November 22nd , 2021:
- Continue drainage repairs on Williams Road
Week of November 29thth , 2021:
- Continue drainage repairs on Williams Road
9/09/21: 2 Week Look Ahead
Week of September 13th , 2021:
- Continue paving and begin driveway and curb restoration on Great Neck Road, Laurie Road, Woodmere Drive and Fawn Circle
- Begin milling on Botsford Place, Ochsner Place and Gorham Place
Week of September 20th , 2021:
- Continue driveway and curb restoration on Great Neck Road, Laurie Road, Woodmere Drive and Fawn Circle
- Begin paving on Botsford Place, Ochsner Place and Gorham Place
8/09/21: 2 Week Look Ahead
Week of August 9th , 2021:
- Begin milling of Shelton Road
- Begin milling various sections of Daniels Farm Road between Daniels Farm School and Wareham Place
- Begin milling Great Neck Road, Laurie Road, Woodmere Drive and Fawn Circle
- Begin drainage repairs on Botsford Place, Ochsner Place and Gorham Place
Week of August 16th , 2021:
- Begin paving of Shelton Road
- Begin paving various sections of Daniels Farm Road between Daniels Farm School and Wareham Place
- Begin paving Great Neck Road, Laurie Road, Woodmere and Fawn Circle
- Continue drainage repairs on Botsford Place, Ochsner Place and Gorham Place
6/16/21: 2 Week Look Ahead
Week of June 21st , 2021:
- Begin milling of Canoe Brook Rd, Anita Ave, Claire Place, Rosellen Dr and Madison Ave from Station Hill to Buck Hill Road
Week of June 28th , 2021:
- Continue milling of Canoe Brook Rd, Anita Ave, Claire Place, Rosellen Dr and Madison Ave from Station Hill to Buck Hill Road
- Begin paving binder course of Canoe Brook Rd, Anita Ave, Claire Place, Rosellen Dr and Madison Ave from Station Hill to Buck Hill Road
4/16/21: 2 Week Look Ahead
Week of April 19th , 2021:
- Begin reclaiming of Glenbrook Road, Aragon Drive and Rangely Drive
- Drainage repairs to continue on Teller Road, Beach Hill Road and Stirrup Drive
Week of April 26th , 2021:
- Continue reclaiming of Glenbrook Road, Aragon Drive and Rangely Drive
- Begin paving of Glenbrook Road, Aragon Drive and Rangely Drive
- Drainage repairs to continue on Teller Road, Beach Hill Road and Stirrup Drive
8/19/20: 2 Week Look Ahead
Week of August 17th , 2020:
- Paving top course of Old Dike Road and Dale Road
- Drainage repairs to continue on Wordins Lane
- Landscaping of Merrill Road, Chatfield Drive, Elmwood Road, Green Street and Walnut Ave
Week of August 24th , 2020:
- Milling to begin on Abric Drive, Bonheur Road, Campbell Road, Fieldstone Court, Gaylord Road, Hitching Post Lane, Leighton Road, Plattsville Road, Richfield Road, Shelbourne Road and Winslow Road
- Paving to continue on Dale Road
- Driveway apron repairs on Old Dike Road and Dale Road
- Drainage repairs to continue on Wordins Lane
7/28/20: 2 Week Look Ahead
Week of July 27th , 2020:
- Paving of driveway aprons and hand work to begin on Green St, Walnut Ave, Elmwood Ave, Merrill Road, Chatfield Drive, Maymount Lane, Dayton Circle and Dale Road
- Continue drainage repairs on Winslow Road, Leighton Road, Gaylord Road and Shelbourne Road
- Milling of Old Dike Road to begin
Week of August 3rd , 2020:
- Paving of driveway aprons and hand work to continue on Green St, Walnut Ave, Elmwood Ave, Merrill Road, Chatfield Drive, Maymount Lane, Dayton Circle and Dale Road
- Continue drainage repairs on Winslow Road, Leighton Road, Gaylord Road and Shelbourne Road
- Milling of Old Dike Road to continue
7/15/20: 2 Week Look Ahead
Week of July 13th , 2020:
- Begin installing curbing on Green St, Walnut Ave, Elmwood Ave, Merrill Road, Maymount Lane, Dayton Circle, Dale Road, Glenbrook Road, Rangely Drive and Aragon Drive
- Continue drainage repairs on Winslow Road, Leighton Road, Gaylord Road and Shelbourne Road
Week of July 20th , 2020:
- Continue installing curbing on Green St, Walnut Ave, Elmwood Ave, Merrill Road, Maymount Lane, Dayton Circle, Dale Road, Glenbrook Road, Rangely Drive and Aragon Drive
- Begin paving top course on Green St, Walnut Ave, Elmwood Ave, Merrill Road, Maymount Lane, Dayton Circle, Dale Road, Glenbrook Road, Rangely Drive and Aragon Drive
- Drainage repairs to continue on Winslow Road, Leighton Road, Gaylord Road and Shelbourne Road
6/22/20: 2 Week Look Ahead
Week of June 22nd , 2020:
- Begin paving binder course on Green St, Walnut Ave, Elmwood Ave and Merrill Road
- Reclaiming of roadway to begin on Maymount Lane, Dayton Circle, Dale Road, Glenbrook Road, Rangely Drive and Aragon Drive
- Drainage repairs to continue on Glenbrook Road
- Drainage repairs to begin on Winslow Road, Leighton Road, Gaylord Road, Shelbourne Road and Hitching Post Lane
Week of June 29th , 2020:
- Continue paving binder course on Green St, Walnut Ave, Elmwood Ave and Merrill Road
- Reclaiming of roadway to continue on Maymount Ln, Dayton Circle, Dale Road, Glenbrook Road, Rangely Drive and Aragon Drive
- Repairs to driveway aprons on Green St, Walnut Ave, Elmwood Ave and Merrill Road
- Drainage repairs to continue on Winslow Road, Leighton Road, Gaylord Road, Shelbourne Road and Hitching Post Lane
6/16/20: 2 Week Look Ahead
Week of June 15th , 2020:
- Drainage repairs to continue on Merrill Road and Chatfield Drive
- Removal of curbs on Green St, Walnut Ave, Elmwood Ave and Merrill Road
- Reclaiming of roadway to begin on Green St, Walnut Ave, Elmwood Ave and Merrill Road
- Drainage repairs to begin on Glenbrook Road
Week of June 22nd , 2020:
- Drainage repairs to continue on Glenbrook Road
- Reclaiming of roadway to continue on Green St, Walnut Ave, Elmwood Ave and Merrill Road
- Repairs to driveway aprons on Green St, Walnut Ave, Elmwood Ave and Merrill Road
5/11/20: 2 Week Look Ahead
Week of May 11th , 2020:
- Saw-cutting of asphalt to begin on Merrill Road and Chatfield Drive
- Drainage repairs to begin on Merrill Road and Chatfield Drive
Week of May 18th , 2020:
- Drainage repairs to continue on Merrill Road and Chatfield Drive
4/01/20: 2 Week Look Ahead
Week of March 30th , 2020:
- Drainage repairs to begin on Maymount Lane and Dale Road
Week of April 6th , 2020:
- Drainage repairs to continue on Maymount Lane and Dale Road
1/10/2020: 2 Week Look Ahead
Winter Shutdown is in effect until further notice
12/20/2019: 2 Week Look Ahead
Week of December 23rd , 2019:
- Drainage Repairs to continue on Madison Ave between Tashua Road and Newton Lane
Week of December 30th , 2019:
- Drainage repairs have been completed on Madison Ave between Tahsua Road and Newton Lane
12/13/2019: 2 Week Look Ahead
Week of December 16th , 2019:
- Drainage Repairs to continue on Madison Ave between Tashua Road and Newton Lane
Week of December 23rd , 2019:
- Drainage repairs to continue on Madison Ave between Tashua Road and Newton Lane
12/06/2019: 2 Week Look Ahead
Week of December 9th , 2019:
Drainage repairs to continue on Campbell Road and Richfield Road
Drainage Repairs to begin on Madison Ave between Tashua Road and Newton Lane
Week of December 16th , 2019:
Drainage repairs to continue on Madison Ave between Tashua Road and Newton Lane
11/27/19: 2 Week Look Ahead
Week of December 2nd , 2019:
- Drainage repairs to continue on Campbell Road and Richfield Road
Week of December 9th , 2019:
- Drainage repairs to continue on Campbell Road and Richfield Road
11/22/19: 2 Week Look Ahead
Week of November 25th , 2019:
- Drainage repairs to continue on Campbell Road and Richfield Road
Week of December 2nd , 2019:
- Drainage repairs to continue on Campbell Road and Richfield Road
11/15/19: 2 Week Look Ahead
Week of November 18th , 2019:
- Drainage repairs to continue on Elmwood and Walnut Avenue
Week of November 25th , 2019:
- Drainage repairs to continue on Elmwood and Walnut Avenue
- Drainage repairs to begin on Campbell Road and Richfield Road
11/08/19: 2 Week Look Ahead
Week of November 11th , 2019:
- Drainage repairs to continue on Elmwood and Walnut Avenue
Week of November 18th , 2019:
- Drainage repairs to continue on Elmwood and Walnut Avenue
- Drainage repairs to begin on Campbell Road and Richfield Road
11/01/19: 2 Week Look Ahead
Week of November 4th , 2019:
- Drainage repairs to continue on Elmwood and Walnut Avenue
Week of November 11th , 2019:
- Drainage repairs to continue on Elmwood and Walnut Avenue
10/25/19: 2 Week Look Ahead
Week of October 28th , 2019:
- Drainage repairs to continue on Abric Drive, Green Street, and Bonheur Road
- Drainage repairs to begin on Elmwood and Walnut Avenue
Week of November 4th , 2019:
- Drainage repairs to continue on Elmwood and Walnut Avenue
10/18/2019: 2 Week Look Ahead
Week of October 21st , 2019:
- Drainage repairs to continue on Abric Drive, Green Street, and Bonheur Road
- Drainage repairs to begin on Elmwood and Walnut Avenue
Week of October 28th , 2019:
- Drainage repairs to continue on Abric Drive, Green Street, and Bonheur Road
- Drainage repairs to continue on Elmwood and Walnut Avenue
9/27/19: 2 Week Look Ahead
Week of September 30rd, 2019:
1. Drainage repairs to continue on Old Dike Road
2. Landscaping and repairs to driveway aprons to begin on Woodridge Circle and Judson Street
3. Landscaping and repairs to driveway aprons to begin on Rocky Hill Rd and Rocky Hill Terrace
4. Drainage repairs to begin on Abric Drive, Green Street, and Bonheur Road
Week of October 7th, 2019:
1. Landscaping and repairs to driveway aprons to begin on Woodridge Circle and Judson Street
2. Landscaping and repairs to driveway aprons to begin on Rocky Hill Rd and Rocky Hill Terrace
3. Drainage repairs to begin on Abric Drive, Green Street, and Bonheur Road